Nijhum Mondol ha creado el proyecto "Tracing a Knit Product's Path: From Buyer Inquiry to Shipment" en Class2Class.org

Solicitar unirse
Inactivo
Público
Trabajar con otra clase

Tracing a Knit Product's Path: From Buyer Inquiry to Shipment

¿De qué trata este proyecto?

Students follow one knit product from buyer inquiry through costing, FOB price negotiation, sample approval, and shipment, documenting each merchandiser decision. They share their timeline with the partner class and evaluate where budget, lead times,...
Edad de los estudiantes
18+ años
Duración del proyecto
12 semanas
Mes de inicio
Diciembre 2026

Este proyecto contribuye a los siguientes objetivos globales

Objetivos de aprendizaje

Students will be able to identify the key stages of a knit product's merchandising path, from buyer inquiry through costing, FOB negotiation, sample approval, and shipment, and share this timeline with the partner class.
Recordar / Comprender
Students will be able to apply costing and FOB price negotiation steps in their team to document merchandiser decisions for one knit product, using budget and lead-time data.
Aplicar
Students will be able to compare their merchandising decisions with the partner class, analyzing how budget, lead times, and coordination risks shaped each final order.
Analizar
Students will be able to evaluate the trade-offs behind their merchandising decisions and propose more effective, intercultural coordination strategies with the partner class to reduce risks in future orders.
Evaluar

Habilidades a desarrollar

Pensamiento crítico y resolución de problemas
Colaboración y trabajo en equipo
Comunicación intercultural
Adaptabilidad y liderazgo
Conciencia global

Actividades del proyecto

1

Meet the partner class and map the merchandising path

Students introduce themselves to the partner class over a video call and sketch the stages a knit product goes through, from buyer inquiry to shipment. Both classes agree on the shared product they will follow.

Duración: 120 minutos
2

Follow the product: inquiry, costing and FOB negotiation

Teams take one knit product through buyer inquiry, costing and FOB price negotiation, recording each merchandiser decision and the budget and lead-time data behind it. They compare notes with the partner class on how they reached their prices.

Duración: 720 minutos
3

Sample approval, production and shipment timeline

Teams build out sample approval, production planning and shipment steps, noting where coordination risks and delays could change the order. They share draft timelines with the partner class and ask for feedback on their decisions.

Duración: 720 minutos
4

Live exchange: compare decisions and trade-offs

Both classes join a live video call to compare their final timelines, discuss where budget, lead times and coordination risks shaped each order, and identify which trade-offs differed across cultures and suppliers.

Duración: 180 minutos
5

Design intercultural coordination strategies

Teams revise their merchandising plan using insights from the exchange and propose concrete coordination strategies to reduce risks in future orders. They test these strategies against the partner class's timeline.

Duración: 720 minutos
6

Present the merchandising timeline and lessons learned

Each team presents its final merchandising timeline, evaluates the key decisions, and shares its proposed coordination strategies with the partner class in a closing video session.

Duración: 240 minutos